Marina Maintenance Program
25/03/2026
E arm exclusion zone

18/03/2026
SYC Marina Project – F Arm Progress Update
Southport Yacht Club is pleased to share that F Arm is nearing completion and looking better than ever, continuing to raise the standard for marina facilities across the Gold Coast.
Southport Yacht Club has seen excellent progress, with Marine Structures and their team streamlining the construction process and improving work sequencing. Combined with favourable weather conditions, this has positioned F Arm to be completed approximately two weeks ahead of schedule.
Elevate Project Services continues to oversee the works on behalf of SYC, ensuring strong quality control and delivery standards are consistently maintained.
In recognition of the progress to date, Marine Structures recently hosted a BBQ for subcontractors, acknowledging the significant effort that has gone into the successful completion of G Arm and the near completion of F Arm.
Brett James (GM), on behalf of the SYC Board and Waterfront Committee, expressed appreciation to Marine Structures and all subcontractors for their work to date, while noting there is still a long way to go until full completion, which is expected late 2027.
The Marina Office will be in contact with all Marina Gold Members regarding any required vessel movements, with ample notice provided to ensure a smooth transition.

18/02/2026
F-Arm piles and pontoons are in and looking good

11/02/2026
F-Arm piles and pontoons moving in.

02/02/2026
Please be advised, E-Arm renovations are scheduled to commence on the 9th APRIL 2026 – Approx Return Date 1st AUGUST 2026. During the works, affected vessels will need to find alternative arrangements to relocate by the 9th APRIL 2026.Unfortunately, the marina is at maximum capacity and are unable to accommodate the temporary relocation of vessels. Any payments that were made for the affected period will be refunded (prorata).
Emails have been sent out to the whole SYC Marina. If you did not get this email, then contact the Marina Office 5591 3500 to ensure you are always up to date with all the latest information.
19/01/2026
F Arm has been emptied and work has begun

18/12/2025
Waterfront Committee and Marine Structures Handover.
The first marina arm handover was completed on 17 December 2025. G Arm was completed on schedule, and the boats will be moving back in from Thursday 18 December 2025.
F Arm will be cleared by 16th of January, with Marine Structures taking possession of the site from Monday 19th January, this section is scheduled to be completed by 21st of April 2026 for handover back to the Club.
Coming up, on the 12th January 2026 we will be relocating the jet ski dock from F Arm across to E Arm for the next stage. During the move your jet ski’s will be unavailable for use, please contact the Marina Office to make arrangements. We don’t anticipate the relocation to take too long.
![]()
12/12/2025
G Arm is on track on the lead up to Christmas (wearing its little red hats!) and The New Year!
Please keep an eye on your emails in case the SYC Marina is trying to contact you regarding the Marina Maintenance Program

01/12/2025
G Arm has now moving along very nicely
Please keep an eye on your emails in case the SYC Marina is trying to contact you regarding the Marina Maintenance Program

27/10/2025
G Arm has now been cleared, ready for the next stage.
Again, please be aware that there will be barges and works around G-ARM EXCLUSION ZONE from now till completion

13/10/2025
Marine Structures has begun works on G Arm, it has now been cleared of vessels. Works will go from 13th October to mid-December this year.
Please be aware there will be barges and works around G Arm EXCLUSION ZONE from now till completion.

For any Marina Maintenance Program related questions please contact enquiries@sycgc.com.au
21/07/2025
07/05/2025
13/03/2025
24/01/2025
23/01/2025
23/01/2025

“Tonight, and tomorrow, we are holding the Marina Maintenance Information Sessions from 5.30pm at Main Beach Clubhouse for all Gold and Sailing Members. This will be an informative night and I hope many of you can attend to hear the information first hand.”
16/01/2025

“For all our Gold and Sailing Members you should have received an email yesterday in regard to the maintenance of the Marina at Main Beach. An information session will be held on January 23rd and 24th to present information and give you the opportunity to ask questions. If you have not received this email, please contact Reception and check the details we have your membership is up to date.”
13/01/2025
Marina Maintenance Information Night and Condition Report Summary